Hva skjer i ZENA?
Skulle ikke boring starte i november 2022?
Produksjonen skulle passere 1000 bor/d lenge nå.
Hvorfor treffer ikke selskapet på noe de guider?
Robbana-3 well (“ROB-3”)
As previously announced, the Company has selected the well location for the
drilling of ROB-3, a new well that will reach a total target depth of
approximately 2,500 metres, following an in-depth geological and reservoir
review enhanced by new information obtained during the workover of ROB-1.
Civil works are expected to begin during the month of September 2022, with a
commercial tender for the selection of a drilling services contractor to be
conducted during the coming months, alongside completion of the necessary local
approval process in accordance with applicable Tunisian legislation.
Drilling activities are expected to commence in November 2022, following the
mobilisation of a drilling rig to the well location.
The necessary long-lead items have already been acquired and are being held in
storage by the Company and funding for ROB-3 is expected to be obtained by way
of the Company's existing cash reserves.
Skulle ikke boring starte i november 2022?
Produksjonen skulle passere 1000 bor/d lenge nå.
Hvorfor treffer ikke selskapet på noe de guider?
Robbana-3 well (“ROB-3”)
As previously announced, the Company has selected the well location for the
drilling of ROB-3, a new well that will reach a total target depth of
approximately 2,500 metres, following an in-depth geological and reservoir
review enhanced by new information obtained during the workover of ROB-1.
Civil works are expected to begin during the month of September 2022, with a
commercial tender for the selection of a drilling services contractor to be
conducted during the coming months, alongside completion of the necessary local
approval process in accordance with applicable Tunisian legislation.
Drilling activities are expected to commence in November 2022, following the
mobilisation of a drilling rig to the well location.
The necessary long-lead items have already been acquired and are being held in
storage by the Company and funding for ROB-3 is expected to be obtained by way
of the Company's existing cash reserves.